Minor Construction Services for a Pouch Vault at the American Embassy Chisinau, Republic of Moldova
Contract# 19GE50-18-C-0028 | Location U.S. Embassy Chisinau, Moldova

August 20, 2018 To Feb 05, 2019

The features of work included, but were not limited to: I- Mobilization temporary site office for technical staffs and demolition of the existing wall and drainage system II- Construction a new small building attached to chancery building IV repair Site drainage system V- construction Force entry wall (FE) RCC wall

Design and construction of Baz International Pharmaceutical Company Compound
Contract# Baz International-Pharma-ACE-2011 | Location Kabul, Afghanistan

Feb 01, 2011 To March 15, 2013

Design and Construction of New building of Baz International Pharmaceutical Company including, 4 story plus basement Main office Building, guesthouse for national and international staff, Construction of access to the warehouse area, Multi-purpose, Water System, Sanitary Sewer System, Site Electrical System, Mechanical system included HVAC system

Design/Build of ANP Border Headquarters in Nangarhar province, Afghanistan
Contract# W917PM-07-C-0053 | Location Nanagarhar, Afghanistan

16 Months

UBG has contracted 4 ANP-BP Headquarters in the Nanagarhar province: 1. Basawal ANP-BP Headquarter 2. Acheen ANP-BP Headquarter 3. Deh Bala ANP-BP Headquarter 4. Door Baba ANP-BP Headquarter Each ANP-BP Headquarter is consists of one administration building, tow barracks buildings, on DFAC, one Latrine/Shower building, POL building, Guard House, Guard shake, Guard towers, Water well house, sidewalks, compound roads, ECP roads, and etc

Chancery Stabilization, Repair and Improvement Project U.S. Embassy Minsk, Belarus
Contract# SGE500-17-C-0051 | Location U.S. Embassy Minsk, Belarus

September 08, 2017 To June 14, 2018

The features of work included, but were not limited to: I- Excavate around the perimeter of the building around the basement and install a new foundation drainage gravity discharge system below the frost line II- Install a storm water collection system with sump pit and pump to collect water from the basement foundation system III- Roof downspouts install routed into the new storm water collection system IV Site drainage system V Gravel access road.

Previous          Next